Hellenic Cables S.A.
The Peloponnese–Crete Interconnection is one of the most important energy projects completed in Greece in recent years. The legal team was involved from the earliest tender stage through to project close-out, developing the subcontracting structure that enabled appointment of a new subcontractor participation and supporting the project throughout execution. Working closely with commercial, technical and project teams, the legal function negotiated key contractual arrangements, managed claims and contract administration, and resolved technical and warranty-related issues without escalation into major disputes. The project shows how early and continuous legal involvement can contribute to the successful delivery of complex infrastructure projects.